Follow

Viewing A Task

When you click through on a task, you will see all of the pertinent details, have the ability to add notes, and update the status.

TaskDetail.png

Mark as Done: Updates the Status to Done and Percent Complete to 100%.

DoneTask.png

You will have the ability to reopen the task if needed.

Edit: You may update any aspects of this task as needed.

Abandon Task: This option is helpful for tasks that are no longer necessary, yet you need to keep a record of it. Abandoning a task will retain the task and update the status to Abandoned.

Delete: Using delete will completely remove the task from the system.

Notes: Simply enter text and press the Add Note button.  The note will be added to the task log and is editable.

TaskNote.png

 

Was this article helpful?